![]() |
The existing New Church was built in 1961 with the "School Room" extension built later in 1968. The large junior church at this time led to the provision of many small rooms with a flat felt roof. Some thirty years on the roof was in need of urgent repair again. The flat roof was replaced in 1986 and if we replaced it again we could expect only a limited life. This alone however did not justify our vision for the buildings. In the same time period there had been loss of community facilities in Nunthorpe, the local institute had to be demolished following a fire and the local library closed after local government reorganisation. |
| A professional architect was appointed and he, working closely with Keith Armstrong and John Wilkinson, carried out the detailed design work. During this phase a series of discussions and presentations were made to church members detailing the progress of the design. There was much discussion about storage ( a problem with the existing building) and the kitchen. The latter was deemed important enough to set up a separate design team. These presentations and discussions provided a mechanism by which all the members could participate in the design process and many features of final design arose as a result. Fundraising also progressed in parallel to the design and we believed that on a rough approximation our estimate of funds available could support the new building. | ![]() |
![]() |
Work on the buildings was scheduled to start on the 17th April 2001. A letter was sent to all residents of Marton Moor Road and Connaught Road advising them of the start of construction and asking for their patience. Complaints have been very few and our thanks go to the local residents who must have had their peace disrupted at times. The early work involved wrecking the roof and the internal walls so all the rooms had to be cleared and the circuit office moved into the Church vestry and choir room. The amount of items that had collected in store cupboards over the last 40 years is difficult to appreciate. We had to be quite ruthless in discarding some items, the remainder were stored in a hired steel container and in member's garages. The construction phase went well. The roof trusses were delivered a few days later than scheduled however it was good to see the pitched roof go on. Following the roof completion the remainder went very quickly. The buildings were handed over for use on the 3rd September 2001 the project having taken about 140 days. |